Bristol’s Pero’s Bridge collapse may have been worsened by loud music

Harbour committee chair Andrew Brown said vibrations from music, wind or traffic could have been the final straw for the damaged footbridge. The exact cause is not known.

Bristol’s Pero’s Bridge collapse may have been worsened by loud music Wolfgang Weiser

Bristol’s Pero’s Bridge collapsed into the harbour on 31 October after possible vibrations from loud music, wind or heavy traffic disturbed the damaged structure, the city’s harbour committee chair has said. Councillor Andrew Brown said those external vibrations could have been the “final straw”, but added that the exact cause of the latest movement could not be confirmed.

The central section fell into the water at about 11pm, days before planned repair work was due to start. The bridge, a city-centre crossing designed to lift for passing boats, had already been left partially hanging after a mechanical failure in the summer.

The loss affects a well-used route between waterfront bars, restaurants and attractions, as well as a crossing for residents and visitors. The bridge opened in 1999 and had been described as being in critical need of repair before the collapse.

What is known about the cause?

Brown said vibrations from speakers on the shore, gusts of wind or nearby heavy road traffic could have affected the bridge’s balance. He did not identify any one of those as the cause, saying: “We cannot be entirely sure of the exact cause of the latest movement.”

In March, the Harbour Committee approved a £1.54m plan to remove the bridge temporarily for repairs. Work was due to begin in November, but the middle section fell before it started. The council has not announced a confirmed cause of the collapse.

How will the bridge be recovered?

Bristol City Council, Bristol Harbour Authority and specialist contractors are working on a plan to remove the bridge spans safely. Four floating rubber fenders, each three metres in diameter, are due to be put in place to help float and stabilise the centre span while preparations for lifting it continue.

Brown said the aim was to return the bridge to use in the harbour for summer 2027. The council has rejected a temporary replacement bridge because of the significant construction cost.

This report draws on information from The Independent.

Editorial checks passed Facts, figures and quotes checked against 1 source